Brockport bridge update

Brockport Village Manager Erica Linden provided an update on the Main Street lift bridge project on July 15.

During the week of July 14, Crane Hogan was slated to continue to finish Punch List work and subcontractors finalize their efforts: BVR Ironworkers re-installing the guide rail, Champion working on the operating console, and O’Connell continuing electrical work.

Electrical testing will continue the week of July 21, with any modifications to be wrapped up Wednesday or Thursday and the operating console work finished Thursday through Saturday.

Functional testing will begin July 28, including nighttime testing, with the bridge in the lowered position. Testing will include warning gates and barrier lights. Temporary warning lights for mariners will be installed.

The bridge is scheduled to open mid-week the week of August 4.

Provided information